What Is a Unit Price Contract in Construction

Unit price contracts are a popular choice in the construction industry for their ability to handle projects with variable scopes. Imagine you’re managing an infrastructure project with unpredictable quantities, how can you ensure fair pricing and cost transparency? This is where unit price contracts excel.

In this blog, we’ll break down what a unit price contract is, how it works, and why it might be the perfect fit for your next project.

A unit price contract is a type of construction agreement where the project cost is based on predetermined rates for specific work units. Each “unit” represents a measurable, repetitive element of the project, such as cubic yards of concrete, tons of gravel, or square footage of drywall. This approach ensures clients pay only for the actual quantities used, offering flexibility for projects with varying scopes.

However, it’s important to consider the risks. A study by the American Society of Civil Engineers found that unbalanced bidding in unit price contracts can lead to cost increases and budget overruns. Being aware of these risks helps both contractors and project owners manage unit price contracts more effectively.

Unit price contracts operate by dividing a project into measurable units. Here’s how it typically works:

  1. Estimation: Contractors and clients agree on unit rates for specific items, like square footage of drywall or tons of gravel.
  2. Execution: As work progresses, the actual quantities of each unit are measured and recorded.
  3. Payment: Clients are billed based on the agreed rates, with final costs calculated by multiplying the actual quantities used by the unit rates.

For example, in a road construction project, if 500 cubic meters of asphalt are needed at $50 per cubic meter, the final cost will adjust according to the actual amount used.

Unit price contracts are beneficial to both project owners and contractors. Here are some of the advantages of unit pricing:

ContractorsProject Owners
Predictable Revenue
Contractors can predict payments based on the actual quantities of work completed.
Cost Control
Project owners only pay for the work that is actually completed, ensuring cost management.
Flexibility in Adjustments
The contract allows for easy adjustments to scope and work volume.
Transparency in Billing
Clear, measurable work units make billing easy to track and understand.
Minimized Risk of Overruns
The unit price structure reduces the likelihood of being underpaid for unexpected work or changes in the project scope.
Fair Payment Structure
Payments are tied directly to completed quantities, ensuring owners pay a fair price for the work done.
Incentive for Efficiency
Contractors can maximize profits by completing tasks efficiently.
Flexibility in Scope Changes
Unit price contracts allow for easy adjustments to project scope without renegotiations.

Unit price contracts can offer flexibility and cost savings, but they also come with their own set of challenges. It’s important to recognize these issues and find ways to address them for a smooth project. Here are some the disadvantages for both contractors and project owners:

ContractorsProject Owners
Potential for Disagreements Over Quantities
Disputes over measurements and quantities can lead to delays and potential loss of payment.
Risk of Overpayment for Misestimated Quantities
If initial quantities are misjudged, project owners may end up paying more than expected.
Risk of Inaccurate Estimates
Contractors may be at a disadvantage if initial estimates for quantities are too low or inaccurate, leading to financial strain.
Potential for Delays
Disagreements over quantities or measurements can cause project delays.
Increased Administrative Work
Continuous tracking, measuring, and reporting of quantities can increase administrative workload and require additional resources.
Uncertainty in Final Costs
While unit prices allow flexibility, the final cost of the project can still be hard to predict, especially if the scope grows unexpectedly.
Cash Flow Risks
While unit prices are predictable, cash flow can be inconsistent if quantities fluctuate or if the project faces delays.
Overemphasis on Quantity Over Quality
Contractors might focus more on completing units rather than maintaining high-quality work, as they are paid based on volume.

Unit price contracts are ideal for:

  • Projects with Unpredictable Scopes: Examples include excavation, infrastructure development, or utility installations.
  • Long-Term Projects: Where adjustments are inevitable over time.
  • Cost-Transparent Clients: Clients who value detailed cost breakdowns.

The unpredictability in these projects means that the final quantities can’t be accurately predicted, making unit price contracts the most flexible option

In construction, the choice of contract type depends on the project’s needs. Construction contracts come in various forms, with unit price contracts being just one option. Here’s how they compare to other common contract types:

Unit Price vs. Lump Sum Contracts

Lump Sum Contracts offer a fixed total price for the entire project, regardless of the work completed. In contrast, a Unit Price Contract adjusts the cost based on the actual quantities of work done, ensuring clients only pay for what’s used. This makes Unit Price Contracts ideal for projects with variable scopes, while Lump Sum Contracts shift the risk of extra costs to the contractor.

Unit Price vs. Cost-Plus Contracts

Cost-Plus Contracts require clients to pay for the actual costs of labor and materials, plus a markup for the contractor’s profit. This can lead to higher expenses if the project extends beyond the initial plan. In comparison, a Unit Price Contract uses set rates for each unit of work, providing more predictable costs as work progresses.

Unit Price vs. Time and Materials Contracts

Time and Materials Contracts bill based on the actual time spent and materials used, which can result in higher costs if the project runs longer. A Unit Price Contract, however, charges based on specific work units, offering a more predictable and transparent cost structure.

To better understand the practical application of unit price contracts, let’s take a look at a hypothetical construction project where this contract type proves to be highly effective.

The city council hires GreenBuild Contractors to develop a new public park. The scope includes laying pathways, planting trees, and adding benches, but due to unpredictable weather conditions and varying terrain, the exact quantities of materials are difficult to estimate. Knowing that the amount of work could change as the project moves forward, GreenBuild suggests using a unit price contract to give both sides the flexibility they need.

The city agrees to the contract, which outlines a set rate for each specific unit of work, like the square footage of pathway or the number of trees planted. Though GreenBuild estimates the materials and labor required, they acknowledge that the final amount may differ as the work progresses. The agreement also includes overhead and profit margins, so everyone is clear about the pricing from the start.

As construction begins, GreenBuild keeps detailed records of the actual quantities used, including the amount of concrete poured and the number of plants installed. The city receives regular invoices that break down the cost of each completed unit of work. This method gives the city full visibility into the project’s progress, ensuring they’re only paying for what’s actually done.

Midway through the project, the city council decides to add a community garden. Because the unit price contract is already in place, this addition is simple to incorporate. The contractor just bills the city for the extra work once it’s finished, using the same unit prices already agreed upon. There’s no need for renegotiation or delays.

Once the project is finished, GreenBuild submits a final invoice reflecting the total cost of the park, which includes the original work and the added garden. The city inspects the finished park and approves payment, knowing that the costs were fair and transparent throughout the project.

To avoid common issues in a unit price contract and keep the project running smoothly, consider these straightforward solutions:

  • Check Measurements Carefully: Always double-check quantities with accurate tools. This ensures the correct amount of work is measured, preventing disputes over pricing.
  • Keep Good Records: Document all work completed, materials used, and any changes to the project. Good records help avoid misunderstandings and provide transparency for both parties.
  • Track Material Costs: Watch for changes in material prices throughout the project. If prices go up, make sure your contract allows for adjustments to unit rates, so everyone stays on the same page and within budget.

By following these tips, both contractors and clients can keep the project on track and avoid common issues

Is a unit price contract the same as an hourly price contract?

No, they’re different. A unit price contract charges based on the amount of work done, like per square foot or ton of material. An hourly price contract charges based on the time spent on the project, usually at an hourly rate.

How do I negotiate better unit rates?

Obtain multiple quotes and analyze market trends to secure competitive pricing.

What happens if quantities change significantly during a project?

The contract allows adjustments based on actual measurements, ensuring fair pricing for both parties.

Unit price contracts provide flexibility and transparency for construction projects with varying quantities. By understanding how they work, their advantages, and how to tackle common challenges, both contractors and clients can ensure smoother project execution. With Builtfront, you can streamline contract management, ensuring accurate tracking, organized documentation, and seamless communication throughout.